Development progress

Where the development stands today

The scheme design is complete and the project is working through environmental and planning approvals. Construction has not started, and no completion date is published until the programme is confirmed after contractor selection.

Current stage
Design and approvals stage
Stages complete
1 of 5
Units planned
30
Construction
Not started
Completion date
On confirmation
Status reviewed
24 September 2026

Implementation sequence

From scheme design to handover

The programme below is the project implementation sequence. Only stages that are actually signed off are marked as completed.

  • Completed
  • In progress
  • Planned
  1. 01

    Scheme design

    Completed

    Site appraisal, unit mix, architectural layouts and the design approach that fixes what is being built at Michamvi.

    • Site appraisal and development brief
    • Unit mix: 10 two-bedroom and 20 three-bedroom apartments
    • Architectural layout drawings: site plan, apartment types and common facilities
    • Structural, roofing and finishes approach
    • Order-of-magnitude cost planning
  2. 02

    Environmental and planning approvals

    In progress

    Statutory submissions to the relevant Zanzibar authorities so the scheme can be permitted as designed.

    • Environmental submission and review
    • Planning approval of the scheme
    • Coordination with the relevant authorities and utility providers
  3. 03

    Detailed design and tender

    Planned

    The approved scheme is developed into construction documentation and priced by contractors.

    • Detailed architectural, structural and services drawings
    • Specifications and schedules
    • Bills of quantities
    • Tender issue and contractor pricing
  4. 04

    Building permit and contractor selection

    Planned

    Permit in place and a contractor appointed against a confirmed construction programme.

    • Building permit issued
    • Contractor appointment and contract signing
    • Confirmed construction programme and site set-up
  5. 05

    Construction and defects liability period

    Planned

    Delivery of the 30 apartments, shared facilities and site infrastructure, followed by the defects liability period.

    • Substructure, superstructure and roofing
    • Finishes, services and joinery
    • Pool, gym, wellness suite and convenience store fit-out
    • Landscaping, parking and site infrastructure
    • Practical completion, handover and defects liability period

What this means for buyers

Buying before completion

Buying during the design and approvals stage is normal for a development of this kind, but it changes what you should check before paying a deposit.

Read carefully

This information is provided for general marketing purposes only and does not constitute an offer, contract or warranty. Architectural drawings, renders, dimensions, finishes and amenities are indicative and subject to change during detailed design, statutory approvals and construction. Unit availability and selling prices are confirmed in writing by Mohafrin.

Ask us for

Latest approvals position
On request
Confirmed construction programme
After contractor selectionPublished once the programme is fixed
Payment structure and milestones
On enquiry
Unit availability schedule
On enquiry
Unit-level specification
On reservation

Anything that affects a purchase decision is confirmed in writing before you commit. Ask us for the current position rather than relying on an older copy of this page or of the brochure.

Kept up to date

Michamvi Apartments

As each stage is completed we update this page, and the status above is dated so you can see how current it is. For anything that affects a purchase decision, ask us for the confirmed position in writing.

Michamvi Apartments Development Brochure

The Mohafrin brochure for the Michamvi Apartments Development, issued as a printable PDF.

Format
PDF, 28 pages
File size
6.0 MB
Edition
24 September 2026

mohafrin-michamvi-apartments-brochure.pdf

Prices, unit availability and the confirmed construction programme change during the sales period, so ask us for the latest written confirmation rather than relying on any document alone.